Whose side is the Architect on?
Question: We are a developer specializing in
strip retail centers. Because of the soft construction market,
we have had quite a number of unfamiliar general contractors
bid on projects. These new players are hungry for work and
often submit bids that are extremely competitive. We always
go with the low bidder and have had no problems until now.
The general contractor on our most recent project has been
getting approval for questionable change orders, many of
which could easily qualify as being part of the original
scope of work, and has received payment for the percentage
of work that we feel has not been done yet. This is a problem
for us as we believe he is taking advantage of the architect
because the architect is able to make independent decisions
on the project. To make things worse, the architect that
we hired seems to side with the contractor quite a bit when
we have a disagreement with the contractor. The architect
has worked with this contractor in the past, and we used
the architect’s recommendation in our final decision
to award the work to this contractor.
It is frustrating
to pay for the expertise of an architect, only to see him
defend the failings of the general contractor. The expression
“bite the hand that feeds you” seems to sum
up our relationship with the architect. The project is barely
halfway completed and we are almost at the point of firing
the architect for his lack of loyalty. Is there anything
we can do to get our architect to see things our way without
derailing the project?
Answer: Before you point the finger at your architect, you
need to understand what the architect’s role is. You
seems have hired the architect to design the project and
then to stay involved with the project during construction
in a contract administration capacity. The architect is
acting as your agent when approving change orders and pay
applications. And, for this project, it seems you have also
given the architect the responsibility to resolve disputes
between you and the contractor.
In that capacity, the architect
is considered a quasi-judicial officer, or in simpler terms,
an arbitrator between you and the contractor to resolve
disputes. In all of these roles, the architect must always
act in good faith and be careful not to act negligently
either in the providing of plans, or approving the contractor’s
pay requests. If there is negligence, then the architect
risks being liable not only to the owner, but also the contractor,
or even the contractors’ surety in cases where the
approved pay application exceeds the actual value of work
done. The architect may also be liable to the contractor
for causing the contractor increased costs and delays due
to excessive time to review submittals or provide responses
to critical requests for information. And, much to your
dismay, when making decisions as to who is correct in a
dispute between the owner and contractor, the architect’s
duty is not just to the owner.
The architect must also consider
the interests of the contractor as well. Even though the
architect has no direct contractual relationship with the
contractor, he owes a duty to the contractor to be fair
and impartial when resolving a dispute. Thus, the architect
has to walk a fine line between the owner and the contractor.
Keep in mind that just because you have paid the architect’s
fee, you cannot demand that the architect do only what you
want it to do if doing so violates the architect’s
legal obligations. By the facts you have provided, it does
not seem to be a wise move to terminate the architect solely
for his lack of loyalty to you. You could be in breach of
contract by doing so, and your worries about whether or
not the project will be completed “on-time and within
budget” will be replaced with worries about the cost
of litigation, which is where everything would probably
end up. In the future, you may consider not having the architect
play such an involved role during construction.
Your own
project manager can decide whether or not to approve a change
order submitted, or deny a claim for extra money or time,
as well as approve the pay applications. However, I am guessing
that you wanted to have the architect be actively involved
during construction in order to relieve your company of
additional administration work. But, as you are finding
out, it sometimes comes with mixed results — especially
when you want to be in control. If you would like to keep
the architect involved during construction, you can have
a contract provision with the contractor as to how to handle
the dispute if one of the parties does not agree with the
architect’s decision. There are also contract provisions
you can use that would make the architect’s decisions
on change orders and pay application subject to final approval
by the owner.
That way, all the parties, including the architect,
have a clear guide in how to handle these issues. A reader
(in response to last week’s article “Liquidated
damages —who do they protect?”) asked: “If
LDs are imposed, would it also be acceptable/advisable for
the GC to propose performance bonuses in the event the project
timeline is ultimately shortened?” Answer: There is
nothing wrong with asking for a bonus for reducingthe project
schedule. What ultimately will dictate whether the owner
agrees to it or not depends on the type of project. For
example, an industrial project where there is going to be
machinery that has a long lead time, or where tenants have
leased the building on a certain date will probably not
benefit by finishing early. On the other hand, if your portion
of the work is on the critical path, and it will be apparent
that the owner will benefit by being up and running earlier
than originally planned, you may be able to attract interest
in a bonus for early completion. Some public works projects,
like those through Caltrans, can have substantial early
completion bonuses in their contracts, making it very lucrative
for a savvy contractor to find ways to complete the project
early.
Do you have a construction question? Submit it to:
info@construction- laws.com • • • Disclaimer
The information in this article is based upon California
law and is for general information only. Any information
or analysis presented here is intended solely to inform
and educate the reader on general issues. Nothing presented
or referenced to, regarding facts, documents or applicable
laws, constitutes legal advice. Before acting or relying
on any information, including any information presented
here, consult with a qualified attorney for your specific
situation. Scholefield holds an active PE license in Colorado,
an undergraduate engineering degree from the University
of Florida, and received her JD from the University of San
Diego. Source Code: 20080411tca
We are...
Anything But
Typical
Call us now to discuss how you can benefit
by using a different approach to managing your legal needs.
info@construction-laws.com |