| 
                    
                  
                    
                  
                   
                    
                  
                    20-day preliminary notices — 
                      when is late ‘too’ late? 
                       
                      Question: We are a tiling contractor and 
                      have never been in the habit of sending out preliminary 
                      lien notices. In the past we have been fortunate to work 
                      with people we have done business with before, but with 
                      today’s shortage of projects, we are doing work with 
                      some new customers. We started a project about a month ago, 
                      but had not done a preliminary notice. Even though we were 
                      paid out first progress payment, which was about 20 percent 
                      of the value of our contract, we’ve heard through 
                      the grapevine that some of the other contractors have not 
                      been paid all of their progress payments. 
                       
                      So, I went ahead and had a preliminary lien notice sent 
                      out through a lien service that charges a minimal amount 
                      to prepare and serve the preliminary notice. That was the 
                      easy part. I was at the jobsite yesterday to look over the 
                      progress of our work and ran into an owner of a plumbing 
                      company I know. We got to talking about the recent difficulties 
                      of collecting payment on some projects and I told him that 
                      I just sent out our preliminary notice and he said “you 
                      shouldn’t have bothered, you’re too late. You 
                      had to send a preliminary notice within 20 days of first 
                      starting your work. Why do you think they call it a ‘20-day’ 
                      preliminary notice? Because you waited 30 days, you have 
                      no mechanics’ lien rights.” 
                       
                      I am not familiar with preliminary notices and liens because 
                      we’ve never had to use them to get paid, so that never 
                      occurred to me. But, it seems pretty unfair that I lose 
                      all my lien rights because I am a measly 10 days late. Is 
                      the plumber right — did I really blow it?  
                       
                      Answer: As usual, there are several possible 
                      answers to your question. The short answer is that the plumber 
                      is right and wrong. He’s right about the name — 
                      a 20-day preliminary notice means it should be served within 
                      20 days of when you first provide materials, labor, equipment 
                      or any other services to the jobsite. But, all is not lost 
                      just because you waited 30 days. A late preliminary notice 
                      does have some effect, but it only covers the work provided 
                      in the previous 20 days and forward.  
                       
                      For example, let’s say you first provided some sort 
                      of work on February 29 (Friday). Perhaps that is when you 
                      had the first load of tile delivered to begin installation 
                      the next Monday (March 3). Because you first provided materials 
                      on Feb. 29, the 20-day clock starts to run on that day. 
                      Then, you wait 30 days, until March 28, to serve the preliminary 
                      notice. Because you were late, the notice only covers work 
                      provided in the previous 20 days, plus anything after you 
                      served the preliminary notice.  
                       
                      So, for our example, assume you have a contract worth $200,000. 
                      Your first load of tile was worth $35,000, and you had four 
                      tile setters working every day, five days a week for the 
                      last four weeks at $37 per hour. So, counting backwards 
                      from March 28, your lien rights only cover from March 8 
                      forward. This means you lose lien rights for the $35,000 
                      of tile and five days of labor costs for four tile setters, 
                      eight hours a day, working March 3, 4, 5, 6 and 7 - or about 
                      $5,920. So, out of a $200,000 contract, you would not have 
                      lien rights for $40,920. But, you are in luck because you 
                      said you were paid your first progress payment. So in my 
                      example, and probably in your real-life situation, you have 
                      already been paid for the materials and labor that you provided 
                      in the first 10 days. Thus, the fact that you may not have 
                      lien rights for what you provided in those first 10 days 
                      it doesn’t matter because you’ve been paid for 
                      that work. 
                       
                      I also noticed that you referred to yourself and other specialty 
                      trades as“contractors” instead of “subcontractors.” 
                      Does this mean that the property owner acted as an owner-builder 
                      and hired each of the trades directly? If that is the case, 
                      then a contractor who has entered into a contract directly 
                      with an owner (called an “original contractor” 
                      under the mechanics’ lien laws) does not have to serve 
                      a preliminary notice at all in order to have lien rights. 
                      
  This is because the purpose of the 20- day preliminary notice 
                      is to alert the owner that you are out there providing a 
                      certain value of work and if you don’t get paid, you 
                      can lien the property. The theory is if the owner enters 
                      into the contract directly, the owner already has notice 
                      of the value of the work you are providing. 
  Another assumption 
                      I made was that you are talking about a private works project. 
                      For public works, a subcontractor with a direct contract 
                      with the prime or general contractor generally does not 
                      have to serve a preliminary notice in order to have “lien” 
                      rights. But, the “lien” rights referred to involve 
                      stop notices and payment bonds — which are better 
                      left subjects of future articles. In order to not have to 
                      worry about when you do or do not have to serve a preliminary 
                      notice, it is much better to just serve a preliminary notice 
                      for every project you work on. The lien service you mentioned 
                      that you used is a perfect low-cost way to preserve your 
                      lien rights. 
  
                      If you have a construction question, submit it to: info@construction-laws. 
                      com 
                      • • • 
                      Disclaimer The information in this article is based upon 
                      California law and is for general information only. Any 
                      information or analysis presented here is intended solely 
                      to inform and educate the reader on general issues. Nothing 
                      presented or referenced to, regarding facts, documents or 
                      applicable laws, constitutes legal advice. Before acting 
                      or relying on any information, including any information 
                      presented here, consult with a qualified attorney for your 
                      specific situation.
  
                      Scholefield holds an active PE license in Colorado, an undergraduate 
                      engineering degree from the University of Florida, and received 
                      her JD from the University of San Diego. Source Code: 20080328tca 
              We are... 
                Anything But Typical 
               Call us now to discuss how you can benefit by 
                using a different approach to managing to your legal needs. 858-858-613-0888 
                info@construction-laws.com  |