Are public Entities Above the Law?
Background/question: A large school district
advertised for bidders for a five-year maintenance contract
for their district’s HVAC systems. The scope of this
contract is to provide a list of guaranteed prices for common
replacement parts, various smaller new AC units, and flat
rates for specific service and repair tasks. We followed all
of the bidding instructions, provided all of the required
documents and submitted our bid. At the bid opening, we were
the low bidder, yet three months later the district has not
issued a notice of award. The work that would be part of the
maintenance contract is currently being performed by a contractor
that the district has been using all along on a piecemeal
basis. Since the commercial HVAC business is a pretty tight
knit community, it isn’t too surprising that we are
able to get insider information on what is going on.
One of our employees found out that the district is awarding
the work that was supposed to be under this contract by issuing
change orders to existing contracts that are perpetually kept
open. We also suspect that the district is breaking up large
projects into smaller projects in order to avoid having to
go out for an open bid. We believe this to be the case because
last year we inspected a particular administration building
to upgrade to an energy efficient HVAC system and we submitted
a competitive quote of about $150,000. At that time, the district
said that they were going to postpone this project due to
budget problems and mentioned something about putting it out
for open bid once they had an acceptable budget for the work.
The district’s preferred contractor is now performing
the work, and this project was never put out for open bid.
Word on the street has it that the district issued several
separate purchase orders for the equipment and then awarded
additional purchases orders for “phases” of the
labor. Our overall impression is that the district’s
facilities personnel had expected their preferred contractor
to be the low bidder on this longterm maintenance contract,
and going through the bid process was nothing more than a
formality to validate the plan.
For now, the district seems to have found loopholes in the
process by issuing change orders and breaking up the larger
projects into smaller ones, so they can avoid issuing the
award for the maintenance contract to our company. We spent
a significant amount of time and resources preparing a detailed
bid in good faith, which included obtaining special pricing
from the equipment manufacturers and devising creative ways
to optimize our labor. Plus, we also spent money on the required
bid bond. We feel we are entitled to be awarded this contract
since we are the low bidder. What can we do?
Answer: I will assume that you are the lowest
responsible bidder submitting a responsive bid (in public
bid lingo). Most bid documents give a deadline as to when
the district will issue the notice of award. If that time
has passed, you may want to consider a bid protest. I strongly
encourage you to seek the advice of experienced legal counsel
immediately because it is easy to lose your rights related
to this contract as well as make matters worse for yourself
for future bids.
For example, if a state public agency decides
that your protest is frivolous, you have to post a bond at
10 percent of the contract value to proceed with the protest,
and you may end up being classified as irresponsible and then
be barred from future agency contracts. The bid documents
should include bid protest procedures particular to that public
entity. It is very important to follow these procedures to
the letter, especially the protest deadlines because they
tend to be very short.
For example, the bid protest procedures
may give a submission deadline of five days after the bid
opening, which is vastly different than a deadline of five
days after the notice of award is publicized. A bid protest
usually begins with submitting a formal written protest explaining
why you are protesting. Most bid protest procedures provide
a guideline on exactly what information you must provide.
Then, you probably will receive a written response to your
protest, or a notice of a hearing. If you receive a written
response, then you will usually need to submit a formal request
for a hearing within a certain deadline if you do not agree
with the response.
At the hearing, it will feel like a one-sided argument because
the very agency that you feel is violating the law is the
one that will decide if you win your protest. If you don’t
agree with the results of the district’s hearing, you
will have to file a petition for a writ of mandate in Superior
Court, and can seek damages. A writ of mandate is when the
court is essentially forcing a public entity to do what they
are supposed to do, but have not been doing. You may be able
to get the court to mandate that the district will not give
work that was supposed to have been provided under the maintenance
contract to its preferred contractor by using the various
illegal means.
You may also be able to petition the court
to stop the district from illegally splitting up large projects
into smaller ones in order to award the work to its favored
contractor. But, the court cannot force the district to award
a specific contractto you or anyone else. Had the contract
been improperly awarded, the best the court could do is mandate
that the contract be taken away from the bidder to whom it
was mis-awarded. In that type of case, the district would
have probably just re-bid the project.
As far as damages go,
the district had the right to reject all bids and not award
contract at all. Depending on how the court looks at the district’s
lack of either awarding the bid or rejecting all bids, if
you are entitled to damages at all, most likely you will only
get your costs for putting the bid together. You are not entitled
to an award against the district for profits that you anticipated
you would have made off the contract. Public contract laws
are intended to eliminate favoritism, fraud and corruption
in the awarding of public contracts. It is far from a perfect
system, but is the only way we have to attempt to keep a level
playing field. It is your right to expect a fair bidding process,
and it may be worth your while to force the district into
playing by the rules to enhance your chances of future work.
Do you have a construction question? Send it to: info@construction-
laws.com
• • •
Disclaimer The information in this article is based upon California
law and is for general information only. Any information or
analysis presented here is intended solely to inform and educate
the reader on general issues. Nothing presented or referenced
to, regarding facts, documents or applicable laws, constitutes
legal advice. Before acting or relying on any information,
including any information presented here, consult with a qualified
attorney for your specific situation.
• • •
Scholefield holds an active PE license in Colorado, an undergraduate
engineering degree from the University of Florida, and received
her JD from the University of San Diego. Source Code: 20080425tca
We are...
Anything But
Typical
Call us now to discuss how you can benefit
by using a different approach to managing to your legal
needs.
858-613-0888
info@construction-laws.com |